Lien: A verified claim for mechanics lien must be recorded within 4 months of last providing work.
Foreclosure: An action to foreclose a mechanics lien must be filed (and a lis pendens recorded) within two years of last providing work, or within 30 days after a demand to commence the suit pursuant to 770 ILCS 60/34.
SUBCONTRACTOR/MATERIAL SUPPLIER:
Homeowners Notice: Subcontractors supplying services or materials to a single family, owner-occupied residence must notify the occupants that it is supplying services or materials within 60 days from the date of first supplying services or materials.
Notice of Claim: Subcontractors must serve a written notice of the claim on the owner and the lender within 90 days of last performing work or delivering materials.
Lien: A verified claim for mechanics lien must be recorded 4 months of last performing work or delivering materials.
Foreclosure: An action to foreclose a mechanics lien must be filed (and a lis pendens recorded) within two years of last providing work, or within 30 days after a demand to commence the suit pursuant to 770 ILCS 60/34.